Did you know that the City and MWH work with the subcontractors to select project areas that fit the criteria of 90% restoration of 90% of the project area, in under 90 days? Sometimes it can be as little as a single street as a project area. Sometimes up to a city block.

They define 90% of the area, because the lowest points require the most digging, and therefore, the most time. The further away from the low spot, the faster you will be restored.

90% Restoration is defined as 'ready to pave', and doesn't include final sod or paving.

This 90/90/90 plan ensures the minimum possible impact on the lives of the residents in affected areas.